1、 Project Name: Ceramic Road Construction Project in Pingchuan District, Baiyin City
2、 Construction location: The starting point intersects with the existing Long March East Road, and the endpoint intersects with the under construction North Ring Road.
3、 Main basis: Ping Fa Gai Fa [2020] No. 169
4、 Construction content: The total length of the road is 1100.8m, and the width of the road red line is 30m. It adopts a single board section, which is 5m (sidewalk)+20m (roadway)+5m (sidewalk)=30m. It is an urban main road with a designed speed of 40km/h. The project content includes demolition engineering, road engineering, transportation engineering, water supply engineering, rainwater engineering, sewage engineering, lighting engineering, earthwork engineering, and related supporting facilities.
5、 Investment estimation and fund composition: The total investment of the project is estimated to be 28.61 million yuan, and the fund composition includes applying for central special funds and raising funds through multiple channels such as finance.
6、 Project Progress: The demolition of the road north of the railway slab culvert has been completed, and the excavation and backfilling of the road foundation have been basically completed. The removal of electrical and telecommunications poles on the road is currently underway, followed by the laying of the road rainwater, sewage, street lights, and signal light pipeline network.